Question 1
A phased DRM implementation is ready to publish a chart of accounts to consolidation. Its agreed acceptance tests, business sign-off, and recovery rehearsal are complete. An unresolved employee-identifier issue belongs to the next phase; it shares no keys, properties, or interfaces with the account release. The sponsor asks whether today's rollout should change. The implementation lead should:
Show answer & explanation
Correct answer: C - Release the accepted account scope and track the employee issue against the next phase's entry criteria.